Question: 1 / 205

What should a COR do if a contractor consistently misses deadlines?

Ignore the issue to maintain a good relationship

Document instances and address them with the contractor

The appropriate action for a Contracting Officer Representative (COR) when a contractor consistently misses deadlines is to document instances and address them with the contractor. This approach ensures that there is a clear record of the issues, which is vital for accountability and future decision-making. By documenting missed deadlines, the COR can provide factual evidence in any subsequent discussions or performance evaluations and can refer to this documentation if further action becomes necessary.

Addressing the issue directly with the contractor fosters open communication, allowing the contractor to explain any challenges they may be facing and potentially develop a plan to improve performance moving forward. This collaborative approach helps to uphold the integrity of the contract while still maintaining a professional relationship.

In contrast, ignoring the issue to preserve a good relationship could lead to further complications down the line, as unresolved problems may compound and significantly affect project outcomes. Terminating the contract immediately could be premature without first addressing the issues and exploring corrective measures. Requesting a contract extension might not be appropriate if the contractor's performance issues cannot be rectified, as there is no guarantee that the contractor would meet future deadlines. Therefore, documenting and discussing the problems represents the best course of action to ensure compliance and uphold the terms of the contract.

Get further explanation with Examzify DeepDiveBeta

Terminate the contract immediately

Request a contract extension